The channel approaching a H flume should be at least 3-5 times the maximum anticipated head at the point of measurement of the flume (Hmax).  

Approach sections can be provided with Openchannelflow H flumes. They can be integral with the flume - forming one continuous piece - or they can be fabricated separately and bolted to the flume prior to shipment.  

dual h flumes with approach sections

Alternatively, approach sections can be formed onsite out of available materials (plywood is common in field run-off applications - concrete is common at treatment plants).
 


Source:  Gwinn, W., Chute Entrances for HS, H, and HL Flumes, Journal of Hydraulic Engineering, Vol. 110, No. 5, May 1984